Site Preparation

Last week confirmation was given that the new Estimated Time of Arrival of the Temporary Building (TB) is March 2. This is when the TB is due to arrive at the Easy Buildings warehouse.

Easy Buildings are aiming to deliver the TB w/c March 7.

t gives this week to finish the preparation of the site.

3 weeks ago, S.E.L. Clarke cleared and levelled the area around JHM. JHM was then very carefully, and skilfully, moved to one side – the expertise of the Clarke team was much appreciated.

The levelling could then be completed. Road scrapings were delivered the next day to compact the ground.